Ref NoLDC/FD/5/1/5
TitleLDC vs Muir Construction Ltd relating to Eliburn East 3a
Date1979-1992
TermArbitration
Related MaterialSee Board Minutes 11/344 in the year 1992, for a full description of the legal complexities of this case.
AdminHistoryIn 1988 Muir Construction Ltd were contracted for the construction of houses at Eliburn East 3a. The properties were built but a dispute arose over claims submitted by Muir for costs, losses and expenses incurred allegedly as result of extended time granted by the project architect. These claims were not resolved through the contract verification system and the case went to arbitration.

Muir claimed for £144,865. The Corporation felt that it could answer many of Muir's points but, in turn, that the arbiter would find in favour of Muir on several issues, as well as finding the Corporation liable for the expenses of the arbitration. As arbitration cost £700-£1000 a day, and was likely to last a minimum of 21 days, the Corporation decided to offer a settlement of £85,000 to Muir, which was accepted in 1992.
AccessStatusOpen
Extent27 files
ScopeandContent27 legal files relating to arbitration between LDC and Muir Construction Ltd.

1-15. Statement of claims and productions for arbitration.
16-27. Other supporting material used to ascertain the facts for the Corporation's case.